Question: The Project Scope Management Knowledge Area is primarily concerned with: Group of answer choices The scope of work required during the initiation phase Defining the

The Project Scope Management Knowledge Area is primarily concerned with:

Group of answer choices

The scope of work required during the initiation phase

Defining the scope of work that included in the project

Defining the specifications and functionality of the work product

Ensuring that the project includes all the work required, and only the work required, to complete the project