Question: The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given

The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given below Field Report at Day 10 Actual Completion Activity 100 100 100 80 25 0 Cost Incurred 2400 1200 4000 4000 4000 0 Calculate the Earned Value, Planned Value, Cost Performance Index (CPI), Schedule Performance Index (SPI), Cost Variance (CV), and Schedule Variance (SV) for the field report day 10. Show your calculations, and summarize the results on a table