Question: The reason why there are only three ( 0 3 ) baselines is because: ( choose the option which completely explains the question ) a

The reason why there are only three (03) baselines is because: (choose the option which completely explains the question)
a.
Scope, Cost, Schedule are considered the triple constraints and accordingly provide the key performance indicators to measure Project Performance
b.
Scope, Cost, Schedule are considered the triple constraints as part of the Iron Triangle
c.
Scope, Cost, Schedule are considered the baselines and triple constraints and as such accordingly provide the key performance indicators to measure the Project Performance
d.
Scope, Cost, Schedule are considered baselines and as such are used in the monitoring and control process group only

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!