Question: The reservoir ( mentioned in the previous question ) is maintained with a Hydropower Dam system, which has 4 ( four ) concrete penstocks to

The reservoir (mentioned in the previous question) is maintained with a Hydropower Dam system, which has 4(four) concrete penstocks to produce hydropower. Each penstock is 300 meters long, 2.5 meters in diameter, and has an equivalent sand roughness height of 3mm. If each penstock carries a flow of 25m3s, estimate the head loss due to friction in each. (10)