Question: The sequence for the planning and controlling process is: Set objectives, set goals, develop plans, implement plans, evaluate performance, modify goals or plans as needed.
-
The sequence for the planning and controlling process is:
Set objectives, set goals, develop plans, implement plans, evaluate performance, modify goals or plans as needed.
Develop plans, set objectives, set goals, implement plans, evaluate performance, modify goals or plans as needed.
Set goals, set objectives, develop plans, implement plans, evaluate performance, modify goals or plans as needed.
Set goals, develop plans, set objectives, implement plans, evaluate performance, modify goals or plans as needed.