The Shale Oil Company contains several operating units that comprise its Aston, Ohio, manufacturing complex. These units
Fantastic news! We've Found the answer you've been seeking!
Question:
DU5 is the only distillation unit for crude oil in the Aston complex, and its shut down severely affects all other operating units. Some of the production can be compensated by Shale refineries in other locations, but the rest must be processed before the shutdown and stored. Without proper planning, a nationwide shortage of Shale gasoline could occur. The timing of DU5's shutdown is critical, and the length of time the unit is down must be kept to a minimum to limit production loss. Shale uses PERT as a planning and controlling tool to minimize shut-down time. The preventive maintenance for DU5 is as follows.
Time Estimates (days) | |||||
Activities | Opt | Most Likely | Pess | Pred(s) | |
1. Circulate wash water throughout unit | 1 | 2 | 2.5 | - | |
2. Install blinds | 1.5 | 2 | 2.5 | 1 | |
3. Open and clean vessels and columns | 2 | 3 | 4 | 2 | |
4. Open and clean heat exchangers, remove tube bundles | 1 | 2 | 3 | 2 | |
5. Open and clean furnaces | 1 | 2 | 4 | 2 | |
6. Open and clean mechanical equipment | 2 | 2.5 | 3 | 2 | |
7. Inspect instrumentation | 2 | 4 | 5 | 2 | |
8. Inspect vessels and columns | 1 | 2 | 3 | 3 | |
9. Inspect heat exchanger shells | 1 | 1.5 | 2 | 4 | |
10. Inspect tube bundles | 1 | 1.5 | 2 | 4 | |
11. Inspect furnaces | 2 | 2.5 | 3 | 5 | |
12. Retube furnaces | 15 | 20 | 30 | 5 | |
13. Inspect mechanical equipment | 1 | 1.5 | 2 | 6 | |
14. Install new pump mechanical seals | 3 | 5 | 8 | 6 | |
15. Repair instrumentation | 3 | 8 | 15 | 7 | |
16. Repair vessels and columns | 14 | 21 | 28 | 8 | |
17. Repair heat exchanger shells | 1 | 5 | 10 | 9 | |
18. Repair tube bundles, retube | 2 | 5 | 10 | 10 | |
19. Repair furnaces | 5 | 10 | 20 | 11 | |
20. Repair mechanical equipment | 10 | 15 | 25 | 13 | |
21. Test and close vessels and columns | 4 | 5 | 8 | 16 | |
22. Install tube bundles into heat exchanger shells | 1 | 2 | 3 | 18 | |
23. Test and close heat exchangers | 1 | 2 | 2.5 | 17, 22 | |
24. Test and close furnaces | 1 | 2 | 3 | 12, 19 | |
25. Test and close mechanical equipment | 1 | 2 | 3 | 14, 20 | |
26. Test instrumentation | 2 | 4 | 6 | 15 | |
27. Pull blinds | 1.5 | 2 | 2.5 | 21, 23, 24, 25 | |
28. Purge all equipment with steam | 1 | 3 | 5 | 27 | |
29. Start up unit | 3 | 5 | 10 | 28 |
|