Question: The Situation: You are the project manager for constructing a custom house. Your company requires an evaluation of the estimate at completion ( EAC )
The Situation: You are the project manager for constructing a custom house. Your company requires an evaluation of the estimate at completion EAC Since the pool change order described in Week has not been executed, you dont have to change your baseline budget. Everything is going well; even the irrigation well and pump are in early. The EAC should be based on the planned and earned values in WBS PV EV July spreadsheet.
The Assignment: Calculate EAC using the four different formulas. You know that Tropical Storm will impact your cost, so in the Bottomup ETC you add $ to the estimated cost for storm cleanup in WBS item ; thus your Bottomup ETC will be $ higher than the ETC EACAC ie ETC EACAC $ Explain the differences between the four forecasting formulas. Which one would you consider has the most validity? Include at least three credible references in addition to the PMBOK Guide with at least one of these being a peerreviewed journal article. Properly cite your response.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock