Question: The snapback timing method was used to obtain average times for work elements in one work cycle. The times are given in the table below.
The snapback timing method was used to obtain average times for work elements in one work cycle. The times are given in the table below. Element d is a machine controlled element and the time is constant. Elements a b c e and f are operator controlled and were performance rated at ; however, elements e and are performed during the machine controlled element The machine allowance is zero no extra time is added to the machine cycle and the PFD allowance is Determine a the normal time for the cycle and b the standard time for the cycle. If the worker works hours and min during an hour shift, and his performance level is how many pieces are completed?