Question: Question 12 A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(7.5, 15,

Question 12 A project has four major activities.

Question 12 A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(7.5, 15, 22.5), B( 7, 14, 21 ), C(1, 2, 3), D( 13.5, 27, 40.5) weeks. What probability would you assign to a project duration of more than 29 weeks? Not yet answered O a. 0.75 Marked out of 2.00 O b. 0.139 O c. 0.5 Remove flag O d. 0.723

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!