Question: The table below describes the project X Predecessor Duration Variance A - 4 1.7 B - 5 1.5 C - 2 4.1 D B 4
The table below describes the project X
| Predecessor | Duration | Variance | |
| A | - | 4 | 1.7 |
| B | - | 5 | 1.5 |
| C | - | 2 | 4.1 |
| D | B | 4 | 3.2 |
| E | B | 5 | 1.9 |
| F | A | 7 | 2.1 |
| G | D, E, F | 4 | 4.9 |
| H | F, G | 3 | 0.3 |
| I | C | 8 | 3 |
| K | I | 3 | 5.2 |
Based on the information provided, perform the following tasks:
- Draw the AON network and identify the critical path and project duration
- Calculate the probability of the project to be completed by Day 21
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts