Question: The table below details the steps required to build and begin services at a new hospital. Use the information in the table below to: Develop
The table below details the steps required to build and begin services at a new hospital. Use the information in the table below to:
- Develop a process flow chart
- Use the critical path method to determine the process flow time and critical path
| Activity | Description | Immediate Predecessor(s) | Activity Time (in weeks) |
| A | Select administrative and medical staff. | --- | 12 |
| B | Select site and do site survey. | --- | 9 |
| C | Select equipment. | A | 10 |
| D | Prepare final construction plans and layout. | B | 10 |
| E | Bring utilities to the site. | B | 24 |
| F | Interview applicants and fill positions in nursing, support staff, maintenance, and security. | A | 10 |
| G | Purchase and take delivery of equipment. | C | 35 |
| H | Construct the hospital. | D | 40 |
| I | Develop an information system. | A | 15 |
| J | Install the equipment. | E, G, H | 4 |
| K | Train nurses and support staff. | F, I, J | 6 |