Question: The table below gives information about a project which consists of 8 activities and 8 units of resources available each week. Activities Duration Weeks Predecessors

The table below gives information about a project which consists of 8 activities and 8 units of resources available each week.

Activities

Duration Weeks

Predecessors

Resources Required per week

A

3

-

6

B

5

A

4

C

7

A

4

D

3

B,C

6

E

5

B

2

F

4

D

4

G

2

C

3

H

5

A, E, F, G

6

  1. Draw the network diagram, Construct a Gantt Chart and Determine the Slack for each activity.
  2. Construct a time phase resource loading Table. Identify the weeks over commitment exists.
  3. Resource level the above network to match lower levels of resources.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!