Question: The table below gives information about a project which consists of 8 activities and 8 units of resources available each week. Activities Duration Weeks Predecessors
The table below gives information about a project which consists of 8 activities and 8 units of resources available each week.
| Activities | Duration Weeks | Predecessors | Resources Required per week |
| A | 3 | - | 6 |
| B | 5 | A | 4 |
| C | 7 | A | 4 |
| D | 3 | B,C | 6 |
| E | 5 | B | 2 |
| F | 4 | D | 4 |
| G | 2 | C | 3 |
| H | 5 | A, E, F, G | 6 |
- Draw the network diagram, Construct a Gantt Chart and Determine the Slack for each activity.
- Construct a time phase resource loading Table. Identify the weeks over commitment exists.
- Resource level the above network to match lower levels of resources.