Question: The table below gives information about a project which consists of 7 activities and 8 units of resources available each week. Resource Duration Activity (weeks)

The table below gives information about a project
The table below gives information about a project which consists of 7 activities and 8 units of resources available each week. Resource Duration Activity (weeks) Predecessor Required per week A 3 8 B 2 A 8 2 B 3 3 D 5 C c 2 N E 3 A 5 A E 5 3 F 3 E 3 G 1 DF 00 8 What is the first week which experiences a resource shortage