Question: The table below gives information about a project which consists of 7 activities and 8 units of resources available each week Activity Duration (weeks) Resource

The table below gives information about a project
The table below gives information about a project which consists of 7 activities and 8 units of resources available each week Activity Duration (weeks) Resource Predecessor Required per week 8 A 3 B 2 8 2 B 3 D 5 3 2 5 2 E 3 5 F 3 E 3 8 G 1 DF What is the first week which experiences a resource surplus