Question: The table below gives the current jobs in process. What job number should be run first assuming an LS dispatch priority? Job # Remaining Processing
The table below gives the current jobs in process.
What job number should be run first assuming an LS dispatch priority?
| Job # | Remaining Processing Time (min) | Remaining Work Time (min) | Arrival Time | Due Date | Setup Time (sec) |
| 1 | 39.3 | 24.5 | 11/10 6:15 | 11/13 | 33.5 |
| 2 | 38.7 | 24.2 | 11/11 22:27 | 11/24 | 40.1 |
| 3 | 44.4 | 26.4 | 11/09 11:09 | 11/20 | 35.1 |
| 4 | 38.9 | 20.1 | 11/10 13:08 | 11/14 | 45.4 |
| 5 | 48.8 | 26.0 | 11/11 17:44 | 11/29 | 39.7 |
| 6 | 37.8 | 23.7 | 11/09 20:22 | 11/24 | 35.1 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock