Question: The table below gives the precedence chart for a project. Activity Precedes Time ( weeks ) A - 8 B - 3 C A 7

The table below gives the precedence chart for a project.
Activity
Precedes
Time (weeks)
A
-
8
B
-
3
C
A
7
D
A, B
3
E
C
4
F
D
6Activity C
a. is a critical activity.
b. has some slack time.
c. is a non-critical activity.
d. has no slack time.
e. is "a" and "d" only