Question: The table below gives the precedence chart for a project. Activity Precedes Time ( weeks ) A - 8 B - 3 C A 7
The table below gives the precedence chart for a project.
Activity
Precedes
Time weeks
A
B
C
A
D
A B
E
C
F
D
Activity C
a is a critical activity.
b has some slack time.
c is a noncritical activity.
d has no slack time.
e is a and d only