Question: The table below gives the precedence chart for a project. Activity Precedes Time (weeks) A - 8 B - 3 C A 7 D A,

The table below gives the precedence chart for a project.

Activity

Precedes

Time (weeks)

A

-

8

B

-

3

C

A

7

D

A, B

3

E

C

4

F

D

6

1. The project completion time is

a. 19 weeks.

b. 11 weeks.

c. 13 weeks.

d. 17 weeks.

e. indeterminate.

2.The critical activities of the above project are

a. A, D, F.

b. B, D, F

c. A, C, E.

d. A, B, E, F.

e. A, C, E, F

3. Activity C

a. is a critical activity.

b. has some slack time.

c. is a non-critical activity.

d. has no slack time.

e. is "a" and "d" only.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!