Question: The table below gives the precedence chart for a project. Activity Precedes Time (weeks) A - 8 B - 3 C A 7 D A,
The table below gives the precedence chart for a project.
| Activity | Precedes | Time (weeks) |
| A | - | 8 |
| B | - | 3 |
| C | A | 7 |
| D | A, B | 3 |
| E | C | 4 |
| F | D | 6 |
1. The project completion time is
| a. 19 weeks. | ||
| b. 11 weeks. | ||
| c. 13 weeks. | ||
| d. 17 weeks. | ||
| e. indeterminate. |
2.The critical activities of the above project are
| a. A, D, F. | ||
| b. B, D, F | ||
| c. A, C, E. | ||
| d. A, B, E, F. | ||
| e. A, C, E, F |
3. Activity C
| a. is a critical activity. | ||
| b. has some slack time. | ||
| c. is a non-critical activity. | ||
| d. has no slack time. | ||
| e. is "a" and "d" only. |