Question: The table below shows the activities, immediate predecessors, and activity durations of a project. table [ [ Activity , Immediate Predecessor ( s )

The table below shows the activities, immediate predecessors, and activity durations of a project.
\table[[Activity,Immediate Predecessor(s),Time (days)],[A,-,9],[B,A,7],[C,A,3],[D,B,6],[E,B,9],[F,C,4],[G,E F,6],[H,D,5],[I,G,3]]
(a) Choose all the activities in the critical path.
A
B
C
D
E
F
G
H
I