Question: The table below shows the information about a small project. Task Budget Normal Immediate Shortest Time | Acceleration Duration Predecessors Possible (days) |Cost per day
The table below shows the information about a small project.

Task Budget Normal Immediate Shortest Time | Acceleration Duration Predecessors Possible (days) |Cost per day (days) A $200 2 None 2 B $500 5 A 3 $30 C $200 2 B 1 $15 D $400 4 A 4 E $300 3 B&D 1 $20 F $400 4 E&C 2 $40