Question: Consider the following information about a small project: Task Budget Duration ( days ) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A $

Consider the following information about a small project:
Task Budget Duration
(days)
Immediate
Predecessors
Shortest Time
Possible
Acceleration
Cost per day
A $2002 None 2
B $5005 A 3 $30
C $2002 B 1 $15
D $4004 A 4
E $3003 B&D 1 $20
F $4004 E&C 2 $40
a.(4 Points) Identify the critical path by forward and backward paths. For the tasks
that are not on the critical path, identify their slacks.
b.(4 Points) At the end of 8th day, assume the following progress of the project:
i. Tasks A, B, D are 100% completed, and the actual costs spent for them are
$200, $500 and $450, respectively.
ii. Task C is 80% completed, and already cost $100
iii. Task E is 66.67% completed, and already cost $100
iv. Task F is not started yet, and didnt cost anything either.
Evaluate the progress of the project by filling the following blanks (both in the
table and in the sentence below the table):
Task Budget Scheduled
Progress
Performed
Progress
ACWP BCWS BCWP
A $200100%100% $200
B $500100%100% $500
C $20080% $100
D $400100% $450
E $30066.67% $100
F $4000%
Total
The whole project is ____(ahead of/behind) schedule, and ____(above/
under) budget.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!