Question: The table lists the blocks of work for a project, along with their costs, duration in weeks, and their predecessor activities. Activity Time(weeks) Cost Predecessor

The table lists the blocks of work for a project, along with their costs, duration in weeks, and their predecessor activities.

Activity

Time(weeks)

Cost

Predecessor activities

A

2

$5,000.00

B

3

$2,000.00

A

C

1

$3,000.00

A

D

4

$9,000.00

A

E

3

$4,000.00

B

F

6

$7,000.00

C

E

G

2

$5,000.00

D

H

4

$3,000.00

F

G

Draw the network diagram of the project, and select the correct alternative:

The duration of the project in weeks is:

Identify the critical and non-critical activities of the project (you must select one answer for each activity)

Activity A:

Activity B:

Activity C:

Activity D:

Activity E:

Activity F:

Activity G:

Activity H:

Calculate the slack (in weeks) of each block of work (you must select one answer for each activity):

Activity A:

Activity B:

Activity C:

Activity D:

Activity E:

Activity F:

Activity G:

Activity H:

The total cost of the project is in the range:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!