Question: The table lists the blocks of work for a project, along with their costs, duration in weeks, and their predecessor activities. Activity Time(weeks) Cost Predecessor
The table lists the blocks of work for a project, along with their costs, duration in weeks, and their predecessor activities.
| Activity | Time(weeks) | Cost | Predecessor activities | |
| A | 2 | $5,000.00 |
|
|
| B | 3 | $2,000.00 | A |
|
| C | 1 | $3,000.00 | A |
|
| D | 4 | $9,000.00 | A |
|
| E | 3 | $4,000.00 | B |
|
| F | 6 | $7,000.00 | C | E |
| G | 2 | $5,000.00 | D |
|
| H | 4 | $3,000.00 | F | G |
Draw the network diagram of the project, and select the correct alternative:
The duration of the project in weeks is:
Identify the critical and non-critical activities of the project (you must select one answer for each activity)
Activity A:
Activity B:
Activity C:
Activity D:
Activity E:
Activity F:
Activity G:
Activity H:
Calculate the slack (in weeks) of each block of work (you must select one answer for each activity):
Activity A:
Activity B:
Activity C:
Activity D:
Activity E:
Activity F:
Activity G:
Activity H:
The total cost of the project is in the range: