Question: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram

The table shown below, which lists the normal and crash durations, and

 costs for a project, comprising of seven activities, and the network diagram 

The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram for said project. All durations are in days, and all costs are in dollars. The network diagram for the project is also shown below. 1 Activity Immediate Normal Normal Predecessor Duration Cost 6 100 10 3 4 4 7 2 ABCDEFG B J A B, C D D E 200 50 150 250 200 50 4 125 Crash Crash Duration Cost 4 500 10 200 2 300 4 150 450 200 100 71 F 3 7 1 Required: Determine a) The critical path; b) The normal duration and the normal cost of the project; and c) By how many days can this project be crashed, and at what cost,

Step by Step Solution

3.41 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity ES EF LS LF SLACK A 0 6 1 7 1 B 0 10 0 10 0 C 6 9 7 10 1 D 10 14 10 14 0 E 14 18 15 19 1 F ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Banking Questions!