Question: The task duration with standard - practice resource usage is referred to as the: Question 1 1 options: expected task duration nominal task duration crash

The task duration with standard-practice resource usage is referred to as the:
Question 11 options:
expected task duration
nominal task duration
crash duration
normal task duration