Question: The tasks involved in a project, their predecessors, and completion times are given in the following table: Task Tasks that must precede Time to finish

The tasks involved in a project, their

The tasks involved in a project, their predecessors, and completion times are given in the following table: Task Tasks that must precede Time to finish task (days) A 4 B A 3 c A 2 D B 5 E B, C 1 F 3 G E, F 4 H D, E 4 I HG 6 (a) Construct the project network for completing this project (with Activity on node-AON). (b) Find the earliest times, latest times, and slack for each activity. Use this information to determine which path(s) is a critical path and the length of the critical path