Question: The time estimates (in weeks) and precedence relationship between activities are shown below. Activity Optimistic Most Likely Pessimistic Immediate Predecessors A 3 4 8 ----

The time estimates (in weeks) and precedence relationship between activities are shown below.

Activity Optimistic Most Likely Pessimistic Immediate Predecessors
A 3 4 8 ----
B 4 6 8 A
C 1 4 7 A
D 2 3 10 B
E 6 8 10 B, C
F 5 7 12 C
G 2 5 8 D, E, F

What is the critical path? (Type your answer with hyphens between the letters, no spaces)

What is the expected duration of this project, based on the calculated expected time (Te) of the critical path? (weeks, show 1 decimal, e.g., 3.1)

What is the variance of the critical path? (weeks, provide 2 decimals, e.g., 2.12)

What is the probability of completing this project in 19 weeks? (Provide 2 decimals, no % sign, e.g., 2.12 for 2.12%.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!