Question: The time required to complete a project is normally distributed with a mean of 8 0 weeks and a standard deviation of 1 0 weeks.

The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated? a.81.28 b.81.82 c.92.80 d.0.81954