Question: The time required to complete a project is normally distributed with a mean of 8 0 weeks and a standard deviation of 1 0 weeks.
The time required to complete a project is normally distributed with a mean of weeks and a standard deviation of weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be percent sure of finishing by the due date, what due date project week # should be negotiated? a b c d
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
