Question: The time-phased net requirements for the base assembly in a table lamp over the next six weeks are Week 1 2 3 4 5 6

The time-phased net requirements for the base assembly in a table lamp over the next six weeks are Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week. b. Determine the lot sizes using the Silver-Meal heuristic