Question: The total completion time is 2 5 days. Task A is planned to take seven days. Task B is planned to take five days. Task
The total completion time is days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished?Group of answer choicesPositive days slack.Negative days slack.Positive days slack.Positive days slack.e question ki answer okasari chegg lo chusi cheppava exam rasstunna