Question: The total completion time is 2 5 days. Task A is planned to take seven days. Task B is planned to take five days. Task

The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished?Group of answer choicesPositive 16 days slack.Negative 5 days slack.Positive 5 days slack.Positive 3 days slack.e question ki answer okasari chegg lo chusi cheppava exam rasstunna

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!