Question: Time left 0 : 1 3 : 5 5 The total completion time is 2 5 days. Task A is planned to take seven days.
Time left ::
The total completion time is days. Task A is planned to take seven days. Task B is planned to take five days. Task is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. What are the ES and EF times for Task B now that Task A is complete?