Question: The total completion time is 2 5 days. Task A is planned to take seven days. Task B is planned to take five days. Task
The total completion time is days. Task A is planned to take seven days.
Task B is planned to take five
days. Task is planned to take eight days. The tasks have a serial relationship.
Task A takes nine days to
be completed instead of seven days. What are the ES and EF times for Task B
now that Task is
complete?