Question: the valuations in an earned value management analysis: do not include profits but must include overhead costs may include revenue, costs, and profits include only

the valuations in an earned value management analysis:
do not include profits but must include overhead costs
may include revenue, costs, and profits
include only direct costs
must be either profits or revenue