Question: The Work Breakdown Structure (WBS) is a framework that will be used as a basis for further planning activities including all the following EXCEPT: a.
The Work Breakdown Structure (WBS) is a framework that will be used as a basis for further planning activities including all the following EXCEPT:
| a. | developing the project schedule | |
| b. | developing the project cost estimate | |
| c. | identifying key stakeholders | |
| d. | identifying project risks |