Question: QUESTION 9 1 points The Work Breakdown Structure ( WBS ) is a framework that will be used as a basis for further planning activities
QUESTION
points
The Work Breakdown Structure WBS is a framework that will be used as a basis for further planning activities including all the following EXCEPT:
a developing the project cost estimate
b identifying project risks
c identifying key stakeholders
d developing the project schedule