Question: The Work Breakdown Structure (WBS) is a very useful with broad application in project management. Which of the following is NOT among the uses of
The Work Breakdown Structure (WBS) is a very useful with broad application in project management. Which of the following is NOT among the uses of the WBS according to Cleland?
| a. | display relationships between work packages | |
| b. | develop project schedule | |
| c. | provide basis for controlling resources applied to project | |
| d. | determine engagement of stakeholders |