Question: The work breakdown structure ( WBS ) provides a foundation for the project to later develop a responsibility axignment matrix ( RAM ) and to
The work breakdown structure WBS provides a foundation for the project to later develop a responsibility axignment matrix RAM and to allocate resources. Which of the following statements about a WBS is false?
A It is used to build a project schedule.
It is a hier archical representation of deliverables.
With each lower level it breaks a project into greater detail.
b it is a key projectplanning tool.