Question: The work breakdown structure ( WBS ) provides a foundation for the project to later develop a responsibility assignment matrix ( RAM ) and to
The work breakdown structure WBS provides a foundation for the project to later develop a responsibility assignment matrix RAM and to allocate resources. Which of the following statements about a WBS is false?
A With each lower level it breaks a project into greater detail.
B It is a key projectplanning tool.
C It is used to build a project schedule.
D It is a hierarchical representation of deliverables.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
