Question: The work breakdown structure ( WBS ) provides a foundation for the project to later develop a responsibility assignment matrix ( RAM ) and to
The work breakdown structure WBS provides a foundation for the project to later develop a
responsibility assignment matrix RAM and to allocate resources. Which of the following statements
about a WBS is false?
A It is used to build a project schedule.
B With each lower level it breaks a project into greater detail.
C It is a hierarchical representation of deliverables.
D It is a key projectplanning tool.