Question: The work elements, precedence relationships, and task times for production of one unit of our product are shown below: Work Element Predecessors Time in Minutes
The work elements, precedence relationships, and task times for production of one unit of our product are shown below:
| Work Element | Predecessors | Time in Minutes |
| A | None | 3 |
| B | A | 3 |
| C | A | 2 |
| D | C | 4 |
| E | B & D | 7 |
| F | E | 4 |
You are designing the assembly line this product will be manufactured on. Your company works 8 hours per day, 5 days per week, for 47 weeks of the year. Required annual output for this product is 10,400. What is the theoretical minimum number of work stations required on this assembly line? State your answer accurate to 2 decimal places.
Your Answer:
|
|
| Answer |
Step by Step Solution
There are 3 Steps involved in it