Question: their predecessors and their optimistic, most likely, and pessimistic duration. Develop the network for this project; Show the deterministic critical path or paths; Calculate the

their predecessors and their optimistic, most likely, and pessimistic duration.
Develop the network for this project;
Show the deterministic critical path or paths;
Calculate the probability of finishing the project in 28 days;
Calculate the probability of finishing the project on day 35.
\table[[Activity,Predecessor,Duration],[Optimistic,Likely,Pessimistic],[A,-,2,4,6],[B,A,5,7,9],[C,A,3,4,5],[D,A,2,4,6],[E,B, C,1,5,9],[F,C, D,3,6,9],[G,B,5,8,11],[H,G,4,7,10],[I,H, F,3,6,9]]
The following network table represents the activities involved in a project along with their predecessors and their optimistic, most likely, and pessimistic duration.
Develop the network for this project;
Show the deterministic critical path or paths;
Calculate the probability of finishing the project in 28 days;
Calculate the probability of finishing the project on day 35.
\table[[Activity,Predecessor,Duration],[Optimistic,Likely,Pessimistic],[A,-,2,4,6],[B,A,5,7,9],[C,A,3,4,5],[D,A,2,4,6],[E,B, C,1,5,9],[F,C, D,3,6,9],[G,B,5,8,11],[H,G,4,7,10],[I,H, F,3,6,9]]
 their predecessors and their optimistic, most likely, and pessimistic duration. Develop

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!