Question: their predecessors and their optimistic, most likely, and pessimistic duration. Develop the network for this project; Show the deterministic critical path or paths; Calculate the
their predecessors and their optimistic, most likely, and pessimistic duration.
Develop the network for this project;
Show the deterministic critical path or paths;
Calculate the probability of finishing the project in days;
Calculate the probability of finishing the project on day
tableActivityPredecessor,DurationOptimisticLikely,PessimisticABACADAEB CFC DGBHGIH F
The following network table represents the activities involved in a project along with their predecessors and their optimistic, most likely, and pessimistic duration.
Develop the network for this project;
Show the deterministic critical path or paths;
Calculate the probability of finishing the project in days;
Calculate the probability of finishing the project on day
tableActivityPredecessor,DurationOptimisticLikely,PessimisticABACADAEB CFC DGBHGIH F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock