Question: There are 3 paths in a project: Route Duration Variance Route 1 9 1.1 Route 2 15 2.89 Route 3 12 0.89 What is the
There are 3 paths in a project:
| Route | Duration | Variance |
| Route 1 | 9 | 1.1 |
| Route 2 | 15 | 2.89 |
| Route 3 | 12 | 0.89 |
What is the chance that this project will be completed in 16 days? Additionally, what is the amount of time needed for there to be a 90% chance that the project is completed in time?