Question: There are 5 steps involved when defining a project; which of the following is the last? Multiple Choice Develop the responsibility matrix Code the WBS
There are 5 steps involved when defining a project; which of the following is the last?
Multiple Choice
-
Develop the responsibility matrix
-
Code the WBS for tracking
-
Assign the work package to a manager
-
All of these are included in the final step.
-
Assign the cost account to a manager