Question: There are 5 table (T 1 , T 2 , T 3 , T 4 , T 5 ) for 5 works ( 1 ,
There are 5 table (T1, T2, T3, T4, T5) for 5 works (1, 2, 3, 4, 5) .
The units (PB) of the works are different in the benches and the table is given. Determine the plan that assigns the work to the benches with the least total cost, by the assignment method. Calculate the total cost in this case.
|
| 1 | 2 | 3 | 4 | 5 |
| T1 | 9 | 4 | 7 | 2 | 6 |
| T2 | 5 | 2 | 4 | 6 | 1 |
| T3 | 4 | 1 | 2 | 3 | 5 |
| T4 | 6 | 8 | 4 | 7 | 3 |
| T5 | 3 | 2 | 1 | 4 | 2 |