Question: There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 9 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $560, E is $575 and all other activities is : $140 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1400 per week, E is $1680 per week and for all other activities is $280 per activity per week. You have a maximum crashing budget of $3505. The maximum possible reduction in the project duration will be:
a.
5 weeks
b.
6 weeks
c.
2 week
d.
3 weeks
e.
4 weeks