Question: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L- E and A-S-T-E. Activties G, H, J, K, S and I can be crashed

There are four critical paths in a network.
There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L- E and A-S-T-E. Activties G, H, J, K, S and I can be crashed by 33 days. The maximum possible reduction in the project duration will be: O a. 33 days O b. 0 days Oc. Insufficient information O d. 198 days O e. 66 days