Question: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by
There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by 76 days. The maximum possible reduction in the project duration will be:
a.
Insufficient information
b.
456 days
c.
152 days
d.
76 days
e.
0 days