Question: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K- L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed

There are four critical paths in a network.
There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K- L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by 44 days. The maximum possible reduction in the project duration will be: O a. Insufficient information b. days O c. 264 days O d. 44 days O e. 88 days