Question: There are four mass production models M 1 M 2 M 3 and M 4 taking 3 5 2 and four hours of manufacturing time

There are four mass production models M1 M2 M3 and M4 taking 352 and four hours of manufacturing time respectively and their respective due dates to the distributor are 410 nine and seven which priority rule from SPT FCFS CR and EDT you would use while sequencing and why also compute the average job completion time average utilisation factor of average job lateness during for each of the priority rule