Question: There are six jobs as below. The processing time in days) and due date for each job are below. Job B D E F Processing

There are six jobs as below. The processing time
There are six jobs as below. The processing time in days) and due date for each job are below. Job B D E F Processing Time (days) 2 12 4 10 5 8 Due Date (days from present time) 7 16 4 15 10 18 Please use SPT (shortest processing time) priority rule to calculate: (a) the average flow time (b) average tardiness (c) average number of jobs at the work center