Question: There are six jobs as below. The processing time (in days) and due date for each job are below. Job Processing Time Due Date (days
There are six jobs as below. The processing time (in days) and due date for each job are below.
| Job | Processing Time | Due Date (days |
| (days) | from present time) | |
| A | 2 | 7 |
| B | 12 | 16 |
| C | 4 | 4 |
| D | 10 | 15 |
| E | 5 | 10 |
| F | 8 | 18 |
Please use SPT (shortest processing time) priority rule to calculate:
(a) the average flow time =
(b) average tardiness =
(c) average number of jobs at the work center =