Question: There are six jobs as below. The processing time (in days) and due date for each job are below. Job Processing Time Due Date (days

There are six jobs as below. The processing time (in days) and due date for each job are below.

Job Processing Time Due Date (days
(days) from present time)
A 2 7
B 12 16
C 4 4
D 10 15
E 5 10
F 8 18

Please use SPT (shortest processing time) priority rule to calculate:

(a) the average flow time =

(b) average tardiness =

(c) average number of jobs at the work center =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!