Question: * There are three resources available to the project. Activities A and D require one resource to complete while activities B, C, E, and F

* There are three resources available to the project. Activities A and D require one resource to complete while activities B, C, E, and F require 2 resources. Develop a resource-constrained schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Record the early start (ES), late finish (LF) and slack (SL) for the new schedule. Answer questions 5,6, and 7 according to this new schedule. 5. What is the new completion time of the project? A.12 B.13 C.14 D.15 E.166. Which of the following time intervals used 3 resources instead of 2 according to the resourceconstrained schedule? (In which time interval the resources scheduled is 2?) A.4-5(Ending period 5) B.\(5-6\)(Ending period 6) C.6-7(Ending period 7) D.\(7-8\)(Ending period 8) E.8-9(Ending period 9)7. What is the new early start of activity E? A.5-6(Ending period 6) B.\(6-7\)(Ending period 7) C.7-8(Ending period 8) D.8-9(Ending period 9) E.9-10(Ending period 10)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!